Declaration of readiness of the facility for operation

A declaration of readiness for operation is an official document that certifies that construction work at the facility has been completed and the building complies with project documentation, building codes, and standards.

It is submitted to the relevant state authorities for commissioning.

When is a declaration of readiness for operation required?

The declaration is submitted in the following cases:

  • Upon completion of construction of a new facility.
  • After reconstruction, major repairs or technical re-equipment of existing buildings.
  • In case of a change in the functional purpose of the building (for example, conversion of a non-residential building into a residential building).

The main stages of filing a declaration:

1. Preparation of documentation

To submit a declaration of readiness for operation, you must have a full package of documents confirming that the building meets all the necessary standards:

  • Project documentation (construction, reconstruction or overhaul project).
  • Technical passport of the facility (issued by the BTI or a certified engineer).
  • Certificate of readiness of the facility for operation (drawn up based on the results of a technical inspection).
  • Documents of ownership of the land and building.

Do you want to know the cost of services for your situation?

Call a consultant
+38 (050) 697-78-54

2. Technical inspection of the facility

A technical inspector or certified specialist inspects the facility to confirm its compliance with the project documentation and building codes.
Based on the results of the inspection, a certificate of readiness is drawn up and attached to the declaration.

3. Submission of the declaration

  • The applicant (the owner of the facility or the construction customer) submits a declaration of readiness for operation to the State
  • Inspectorate of Architecture and Urban Development (SIAU) or the relevant local government body.
  • The declaration can be submitted either electronically through the e-services portal or in person to the local authority.

4. Verification of the declaration

  • The authorities receiving the declaration check the submitted documents for completeness and compliance with the requirements.
  • If the declaration meets all the requirements and the documents are properly executed, it is considered registered.

5. Decision to put the facility into operation

After the declaration is registered, the facility is considered officially commissioned. The customer receives a corresponding document that allows him to use the facility for living or other activities.

Important points:

  • The declaration is a mandatory step to complete the construction or reconstruction of any facility.
  • Putting a facility into operation without a declaration or certificate of readiness is illegal.
  • Violation of construction standards or submission of false information in the declaration may result in refusal to register it or its revocation after inspection.

Contact GlobalBud Ukraine

Preparing a declaration of readiness for operation is a process that requires accuracy and full compliance with the law. The specialists of GlobalBud Ukraine will help you to prepare all the documents correctly, conduct the necessary technical inspections and ensure the successful submission of the declaration to the relevant authorities.

Need an initial consultation?

We will help you solve the problem within 1 day

    Залиште ваше запитання і ми вам зателефонуємо
    або зателефонуйте самі нам за номером
    +38 (050) 697-78-54


    Наскільки стаття була корисною?

    Натисніть щоб оцінити!

    Середня оцінка / 5. Кількість оцінок:

    Оцінок поки немає. Оцініть першим.

    Слідкуйте за нами в соцмережах

    • Land Plot Investigation and Site Analysis
      Land Plot Investigation and Site Analysis A comprehensive land plot investigation is one of the key stages in preparing for construction, real estate investment, or the implementation of a development project. Before commencing the design phase, it is essential to assess not only the legal status of the land but …
    • Property Handover from a Developer
      Property Handover from a Developer: Why It Matters The acceptance and handover of an apartment, private house, or commercial premises from a developer is one of the most critical stages of acquiring real estate. Before signing the property acceptance certificate, the buyer has the opportunity to identify construction defects, finishing …
    • Comprehensive Instrumental Building Inspection
      Comprehensive Instrumental Building Inspection: What It Is A comprehensive instrumental building inspection is a detailed technical assessment of a property using specialized diagnostic equipment. This type of inspection makes it possible to identify not only visible defects, but also hidden issues related to structural elements, thermal insulation, engineering systems, and …
    • Comprehensive Building Inspection
      Comprehensive Building Inspection: Why It Is Necessary A comprehensive building inspection is a professional assessment of the technical condition of a real estate property that helps identify hidden defects, structural damage, and potential operational risks. Most commonly, such inspections are ordered prior to the purchase of residential, commercial, or industrial …

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    Call Now Button